Multi PU MD
3-4 mm Polyurethane Floor Screed
MULTI PU MD SCREED is a trowel applied polyurethane floor screed for medium to heavy duty industrial use. Highly chemical, abrasion and impact resistant, with a smooth surface for hygienic cleanliness and seamless flooring. Supplied in a variety of colours for use in environments that range from cold rooms to boiler rooms, warehousing to shop floors.
Typical Applications
MULTI PU MD SCREED can be used in food processing plants, cold rooms, canning factories, bottling plants, high foot traffic areas and environments where food safety and medium to heavy industrial use are both prerequisites.
Download our Spec Sheets below:
Description
MULTI PU MD SCREED is a trowel applied polyurethane floor screed for medium to heavy duty industrial use. Highly chemical, abrasion and impact resistant, with a smooth surface for hygienic cleanliness and seamless flooring. Supplied in a variety of colours for use in environments that range from cold rooms to boiler rooms, warehousing to shop floors.
Typical Applications
MULTI PU MD SCREED can be used in food processing plants, cold rooms, canning factories, bottling plants, high foot traffic areas and environments where food safety and medium to heavy industrial use are both prerequisites.
Advantages
- Economical
- High early strength
- High abrasion resistance
- High chemical resistance
- High impact resistance
- High density
- Nonhazardous (food safe)
- Seamless
- Flow applied for rapid installation
- Low maintenance
Silver Ion Technology
For HACCP environments, the inclusion of Silver Ion Technology gives the polyurethane screed permanent bactericidal properties. Only included on request.
Typical Properties
BS 8204-6 |
Type 7 |
Adhesion to Concrete |
>1.5 N/mm2 |
Shore D Hardness |
75 |
Slip Resistance Dry |
>60 |
Slip Resistance Wet |
N/A |
Application Temp. |
15C to 25C |
Surface Finish |
Smooth matt |
Application Thickness |
3-4 mm |
Pot Life |
15 Minutes |
Use Temperature |
-20C to 60C |
Yield |
12 Litres per kit |
Coverage |
3m2 at 4mm thick |
Time to Foot Traffic |
12 Hours |
Time to Wheel Traffic |
24 Hours |
Time to Heavy Traffic |
48 Hours |
Full Chemical Resist. |
7 Days |
Chemical resistance includes citric acid (fruits), vinegar (50% acetic acid), lactic acid (food and diary), alcohols, inorganic acids, fuels, hydraulic oils, mineral oils, aromatic and aliphatic solvents, common alkalis. |
Watch Points
- While polyurethane screeds are chemically resistant, they can still stain and a sealer coat is recommended in areas where concentrated dyes, or foods or chemicals with staining history are exposed to the screeds for long periods of time.
- A formal hygienic cleaning procedure is required to keep the surfaces hygienically clean and food safe.
- Polyurethane screeds are not UV stable and will yellow under bright lighting and sunlight.
Directions for Use
Application Conditions: Application temperature should be between 15C and 25C. Employ the use of localized cooling or heating equipment if necessary. Try avoid applying over hot surfaces or previously heated areas. Substrates must have a moisture content of 12% maximum and tensile strength of 1.5 N/mm2 minimum.
Surface Preparation: Surfaces need to be cleaned and flattened or imperfects will show through flow applied applications. Light grinding to remove all surface defects is recommended. Scabbling and acid etching is not recommended. If the substrate is porous or there is expected to be pin hole issues or moisture concerns, a scraper coat of MULTI PU resin and hardener is recommended as a primer. Anchor grooves are to be cut at twice the thickness of the floor finish to a maximum of 10mm. Anchor grooves are to be cut around the floor perimeter, parallel to expansion joints, around upright structures, around drains, parallel to door thresholds, and at regular 3 meter spacing across the floor surface.
Priming: Use a scraper coat of MULTI PU resin and hardener to prime the floor surface, making sure not to fill anchor grooves. Ensure even coverage using a mohair roller until the surface is completely wetted out. Apply in anchor grooves with a brush. Allow to sure for 12 hours and if dry patches appear, a second application of primer is required. Allow to cure for a further 12 hours. If the primer is left for longer than 48 hours, the primer will need to be abraded and a further coat of primer applied to prevent pin holing of the final screed topping. If moisture is a concern, prime with MULTI PU LC coating at 500 µm thickness using a trowel and allow to cure for 12 hours. If no blistering or pin holing occurs, continue with the final screed topping.
Application: Shake well the resin component to resuspend all the pigments in the liquid. In a pot mixer, premix the resin and the hardener until mixed together. While mixing, add in the powder aggregate gradually until all wetted out and lump free. Then transfer the mix onto the primed surface and level to the required thickness using a steel trowel. Once level, use a spike roller to remove stubborn trowel lines and reaerate the screed. Do not spike roll beyond initial set (3-5 minutes of application) or the screed will not self-level and roll marks will remain in the screed. Ensure that anchor grooves are filled completely. Allow the screed to cure for 12 hours. Protect the curing floor from damp, condensation and direct water for at least 24 hours.
Limitations: Do not apply in humidity is expected to be greater than 90% RH, or if the surface temperature is less than 3C above the dew point. Ensure that the curing temperature never drops below 5C, and do not apply over concrete that is less than 25 MPa compressive strength. Colour variations can occur between batches so apply sections from the same batch of resin. Touching up will always be visible and should be avoided. If colour variations occur, overcoat the entire surface with MULTI PU LC coating. To guard against discoloration from contact with strong oxidizing agents such as halogens, seal with MULTI PU SEALER clear matt. Direct contact with rubber or bituminous type materials will leave black marks within the first month of use as the MULTI PU TF COATING is still actively curing.
Equipment Care
All tools should be cleaned with thinners or xylene immediately after use.
Packing
Supplied in 2.9LT RESIN, 2.1LT HARDENER and 17.5KG AGGREGATE.
REVISION: R3.1
Data sheet
- COLOUR
- Various
- YIELD
- 12L
- PACK SIZE
- 12L